The Associated Press
Boeing lost $425 million in the first quarter -- more than Wall Street expected -- but said Wednesday that it plans to boost production of its best-selling plane, the 737 Max, later this year.
Revenue rose 28% from a year earlier, as airlines scooped up new jets to meet rising travel demand, and the company stood by its forecast of producing $3 billion to $5 billion in cash flow this year.
Shares of Boeing rose nearly 5% before settling to close up less than 1%.
CEO David Calhoun called it a "solid first quarter."
"We continue to make real progress, steady progress, in our recovery," he said on a call with analysts. "Challenges remain, there's more to do, but overall we feel good about the operational and financial outlook."
Boeing's passenger jets have been plagued by production problems, and the quarterly loss was due largely to the cost of reworking planes to fix production flaws. It also took a write-down for a military tanker.
Calhoun said again that Boeing will delay deliveries of some planes that airlines were expecting for the busy summer travel season. The delays are due to unapproved fittings that a contractor, Spirit AeroSystems, installed where the tail meets the fuselage on most 737 Max jets built since 2019.
"It's a gnarly defect," Calhoun said when an analyst asked why it took four years to discover the flaw. The CEO said a sealant applied over fuselage joints hid the cracks.
Analysts expressed some skepticism about Boeing's outlook while problems persist in its supply chain. Seth Seifman of JPMorgan wondered whether Boeing can increase 737 production given issues at Spirit.
"You can only go as fast as they can go, and … I don't think anybody has had a more challenging three or four years than Spirit, other than maybe you guys," Seifman told executives.
Calhoun replied that Boeing is confident Spirit can meet a faster schedule.
Officials said it would take a matter of days to fix planes that are not yet assembled but longer for about 225 Max jets that were finished and are now sitting in Boeing's inventory.
Executives didn't put a precise number on how many 737 deliveries will be delayed beyond the peak summer travel season. Calhoun said last week that 9,000 seats would be missing from airline schedules this summer, which works out to about 50 Max jets.
Despite the setback, Boeing still hopes to hit its goal of delivering 400 to 450 Max jets this year. It delivered 111 in the first quarter.
Boeing said it still expects to increase Max production. The company was building 31 a month at the start of this year and plans to raise that to 38 a month later this year and 50 a month by 2025 or 2026.
Boeing repeated earlier assurances that the fuselage issue on the Max does not affect safety and that airlines can keep using planes that are already carrying passengers.